The Minister of Power, Joseph Tegbe, has commissioned four new power transformers in Gombe State as part of efforts to strengthen electricity transmission capacity, improve grid reliability and boost bulk power supply across the North-East.
The newly inaugurated facilities are expected to improve electricity supply to customers in Gombe, Billiri, Numan and adjoining communities by addressing suppressed demand and increasing transmission capacity within the Jos Electricity Distribution Company franchise areas.
The transformers comprise a 300MVA, 330/132kV and a 100MVA, 132/33kV installed at the Gombe Transmission Substation, as well as two 60MVA, 132/33kV transformers at the Billiri Transmission Substation.
Speaking during the commissioning, Tegbe said the projects demonstrated President Bola Ahmed Tinubu’s commitment to ensuring that no community was denied opportunities for economic growth because of inadequate supporting infrastructure.
He said the investments would strengthen the transmission network serving the benefiting communities while providing additional capacity to accommodate suppressed electricity demand.
According to him, the Federal Government was reinforcing critical transmission infrastructure with clear economic objectives, including improving grid reliability, unlocking stranded capacity and supporting productive economic activities.
The Minister called on host communities to take ownership of the facilities and protect them against vandalism and other acts capable of undermining their operations.
He stressed that safeguarding the infrastructure required the collective vigilance and cooperation of residents in the benefiting communities.
The Emir of Billiri, the Mai Tangle, commended President Bola Ahmed Tinubu and the Minister of Power for the interventions, expressing appreciation for the efforts to provide steady and reliable electricity to the people.
In recognition of the Minister’s contribution to improving power infrastructure, the traditional ruler announced his conferment with the title of “Ambassador of Light.”
Earlier, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria (TCN), Engr. Sule Abdulaziz, said the additional transformer capacities were necessitated by the need to address stranded transmission capacity and suppressed electricity demand in the affected areas, as well as improve flexibility across the network.
Abdulaziz also appealed to members of the host communities to actively protect the power infrastructure against vandalism to ensure the sustainability of the investments and reliable electricity transmission to consumers.